Construction Update 8/21/19

Roadway Improvements: Crews will finish installing the black base at the Atlantic Avenue/Gleason Street intersection today. New curbs at the corners are scheduled to be installed by the end of the week. Crews are scheduled to begin work at the Atlantic Avenue/Venetian Drive intersection Thursday, August 22. This work will be completed in 3 phases… Continue reading

More

Construction Update 8/20/2019

Due to the weather, the Contractor has cancelled today’s work scheduled for the intersection of Atlantic Avenue and Gleason Street. This work is schedule to resume again tomorrow weather pending.

More

Project Update 8/19/2019

Construction Schedule: The Contractor’s work hours are 7:00 AM to 7:00 PM (Monday – Friday), weather pending. Work Completed Last Week Roadway Improvements: Intersection work was cancelled due to weather . Beach Improvements: Dune delineation work including brush trimming near pathways and fence post installation is ongoing. 10% of pathways complete. Work Scheduled for this… Continue reading

More

Construction Update 8/14/2019

Roadway Improvements: The Atlantic Avenue intersection work is scheduled to begin Monday, August 19th. Work will begin at the Atlantic Avenue/Gleason Street intersection and progress to the Atlantic/Venetian Drive intersection as the week continues. This work has been delayed due to the recent afternoon storms. Beach Improvements: The contractor will continue installing the dune fencing… Continue reading

More

Construction Update 8/14/2019

Due to the weather forecast, the work on Atlantic Avenue at the Gleason Street intersection has been postponed for today. Stay tuned for an updated start date.

More

Construction Update 8/13/2019

Wednesday, August 13, 2019 (weather pending), the Contractor (MBR Construction) is scheduled to begin the intersection improvements on Atlantic Avenue at the Gleason Street intersection. The work is scheduled to continue through the week. Atlantic Avenue will remain OPEN to two way (east/west) traffic during construction. Access to Gleason Street may be restricted during the… Continue reading

More

Project Update 8/12/2019

Construction Schedule Update: The Contractor’s work hours have been extended to 7:00 AM to 7:00 PM (Monday – Friday). Work Completed Last Week Roadway Improvements: The contractor mobilized equipment and supplies to the site. Set up maintenance of traffic on Atlantic Avenue in preparation for the upcoming Venetian Drive and Gleason Street intersection work. Beach… Continue reading

More

Public Meeting Powerpoint 7/31/2019

Thanks to everyone who came to the Public Outreach Meeting on 7/31/19. Please Click Here to view the meeting presentation.

More

Project Update 7/26/2019 – Public Meeting on 7/31/2019 Announcement

Construction is scheduled to start on Monday July 29th, 2019.  The City is having another public meeting at 6:00pm on Wednesday, July 31, 2019 to discuss the maintenance of traffic, detours and access during construction for the roadway work at Venetian Drive and Gleason Street intersections with Atlantic Avenue.  CLICK HERE for meeting details.  The… Continue reading

More

Public Meeting Powerpoint 5/28/2019

If you were unable to attend the public meeting on Tuesday, May 28, 2019 and are interested in reviewing the information shared, please CLICK HERE to view the meeting Powerpoint.

More