Overnight Work Postponed Due to Weather

Tonight’s scheduled overnight work has been postponed due to the weather. An updated schedule will be posted when it is available.

More

Project Update 11/14/19

Updated Night Work Schedule Crews continue stamping and painting a red brick herringbone pattern on the new asphalt pavement at the below intersections during night work hours. Temporary lanes closures will be set up with flaggers in place for traffic control. 11:30 PM Thursday (11/14/19) to 9:00 AM Friday (11/15/19) – Intersection of Atlantic &… Continue reading

More

Overnight Work Canceled Due to Weather

The night work originally scheduled for the intersection of Atlantic & Venetian and Atlantic & Gleason has been postponed due to weather. An updated scheduled will posted as soon as it is available. POSTPONED: 12:00 AM to 8:00 AM Thursday (11/14/19) – Intersection of Atlantic & Venetian and Atlantic & Gleason

More

Project Update 11/12/19

Daytime Work Park Benches – Crews will begin today, 11/12/19, removing the current park benches in the Main Pavilion and installing new park benches. Dune Fencing Installation – Crews continue installing dune fencing posts along the back side of the sidewalk on the east side of A1A. Crews are currently working between Thomas St and… Continue reading

More

Project Update 11/8/19

Night Work Scheduled Crews continue stamping and painting a red brick herringbone pattern on the new asphalt pavement at the below intersections during night work hours. Temporary lanes closures will be set up with flaggers in place for traffic control. Updated Schedule 9:00 PM Friday (11/8/19) to 6:00 AM Saturday (11/9/19) – Intersection of Casuarina… Continue reading

More

Project Update 11/7/19

Night Work Scheduled Crews continue stamping and painting a red brick herringbone pattern on the new asphalt pavement at the below intersections during night work hours. Temporary lanes closures will be set up with flaggers in place for traffic control. Updated Schedule 9:00 PM Thursday (11/7/19) to 7:00 AM Friday (11/8/19) – Intersection of Casuarina… Continue reading

More

Night Work Scheduled for this Week

Crews will begin the process of stamping and painting a red brick herringbone pattern on the new asphalt pavement at the below intersections during night work hours. Temporary lanes closures will be set up with flaggers in place for traffic control. Schedule for the week of 11/4: 9:00 PM Tuesday (11/5/19) to 7:00 AM Wednesday… Continue reading

More

Project Update 11/4/19

Daytime Work Planned for this Week Dune Fencing Installation – Crews continue installing the dune fencing rope through the new wooden posts and are adjusting a few of the beach paths. Rope has been installed up to Bay Street, and installation is progressing north. Pedestrian Light Poles – Crews installed all the new light poles… Continue reading

More

Project Update 11/4/19

Dune Fencing Installation – Crews began installing the dune fencing rope through the new wooden posts. Crews began on the south end of the project near Casuarina Rd and are moving north. Pedestrian Light Poles – Crews began installing the new light fixtures on the poles along A1A from Casuarina Rd to Beach Drive. This… Continue reading

More

Project Update 10/31/19

Dune Fencing Installation – Crews continue installing the remaining dune fencing posts along the east side of A1A along the back side of the sidewalk. Crews are working between Atlantic Ave. and Beach Drive. Pedestrian Light Poles – Work continues on the new lighting on the beach side of A1A. Crews began installing the new… Continue reading

More