Overnight Work Postponed Due to Weather

Tonight’s scheduled overnight work has been postponed due to the weather. An updated schedule will be posted when it is available.

More

Project Update 11/14/19

Updated Night Work Schedule Crews continue stamping and painting a red brick herringbone pattern on the new asphalt pavement at the below intersections during night work hours. Temporary lanes closures will be set up with flaggers in place for traffic control. 11:30 PM Thursday (11/14/19) to 9:00 AM Friday (11/15/19) – Intersection of Atlantic &… Continue reading

More

Overnight Work Canceled Due to Weather

The night work originally scheduled for the intersection of Atlantic & Venetian and Atlantic & Gleason has been postponed due to weather. An updated scheduled will posted as soon as it is available. POSTPONED: 12:00 AM to 8:00 AM Thursday (11/14/19) – Intersection of Atlantic & Venetian and Atlantic & Gleason

More

Project Update 11/12/19

Daytime Work Park Benches – Crews will begin today, 11/12/19, removing the current park benches in the Main Pavilion and installing new park benches. Dune Fencing Installation – Crews continue installing dune fencing posts along the back side of the sidewalk on the east side of A1A. Crews are currently working between Thomas St and… Continue reading

More

Project Update 11/8/19

Night Work Scheduled Crews continue stamping and painting a red brick herringbone pattern on the new asphalt pavement at the below intersections during night work hours. Temporary lanes closures will be set up with flaggers in place for traffic control. Updated Schedule 9:00 PM Friday (11/8/19) to 6:00 AM Saturday (11/9/19) – Intersection of Casuarina… Continue reading