Project Update 12/9/19

  • Dune Fencing Installation – Installation is near 95% complete. Crews are currently working near the North End Crosswalk installing the last sections of Dune Fencing. Once the posts are completed, the new rope will be installed.
  • Pedestrian Lighting – The new pedestrian lighting has been turned on and is now fully working. The new lighting runs along the East side of A1A between Casuarina Rd on the South to Beach Drive on the North End.
  • Sidewalk Sealcoating – Crews are applying a new sealcoat to the colored sidewalks along the east side of A1A. Pedestrians walking along the east side of A1A may encounter closed sidewalk sections while the contractor is applying the new sealcoat. Once applied, it takes approximately 4 hours to dry before reopening. This work will be ongoing over the next few weeks as the sidewalks from Casuarina Rd to the North End Crosswalk are sealcoated. Beginning today, 12/9/19, the contractor will be starting at 3:00 am to begin the application earlier for less interference with Beach Traffic during the daytime.

The schedule is weather dependent and is subject to change. Stay tuned for future schedule updates. 

SHARE