Project Update 12/18/19

  • Dune Fencing Installation – Installation is 100% complete.
  • Pedestrian Lighting – The new pedestrian lighting has been completed. The contractor will be making a few minor adjustments to the light fixtures on the top of the light poles in the next couple weeks.
  • Sidewalk Sealcoating – Sealcoating is over 50% complete. The contractor is working between 1:00 am to 5:00 am to apply the new sealcoating with minimal impact to pedestrian and beach traffic. This work is anticipated to be completed this week.

The schedule is weather dependent and is subject to change. Stay tuned for future schedule updates. 