Project Update 11/4/19

Daytime Work Planned for this Week

  • Dune Fencing Installation – Crews continue installing the dune fencing rope through the new wooden posts and are adjusting a few of the beach paths. Rope has been installed up to Bay Street, and installation is progressing north.
  • Pedestrian Light Poles – Crews installed all the new light poles and fixtures along A1A from Casuarina Rd to Beach Drive. Crews are continuing to install the electrical conduits and wiring for the lights this week. This work will have minimal impact to the pedestrian traffic.
  • Solar Bollards – Crews began installing the new solar bollards today. The new bollards will be located around the Main Pavilion at Atlantic Ave. and A1A and the 2 smaller pavilions north and south of the Main Pavilion. Bollard installation was completed today at the South Pavilion.