Project Update 11/27/19

  • Dune Fencing Installation – Crews continue installing dune fencing posts along the back side of the sidewalk on the east side of A1A. Crews are currently working on the last section around Beach Drive to the North End Crosswalk. As sections get completed, crews will again be pulling the rope into place down the Beach Access Paths.
  • Pedestrian Lighting – Crews have been busy getting the final electrical work completed for the new pedestrian lighting along the east side of A1A between Casuarina Rd on the south end to Beach Drive on the north end. We hope to have this new lighting operational during the upcoming Thanksgiving Weekend.
  • Sidewalk Sealcoating – Crews began applying a new sealcoat to the colored sidewalks along the east side of A1A. The first section from Casuarina Rd to near the Anchor Park Crosswalk has been completed. Pedestrians walking along the east side of A1A may encounter closed sidewalk sections while the contractor is applying the new sealcoat. Once applied, it takes approximately 4 hours to dry before reopening. This work will be ongoing over the next few weeks as the sidewalks from Casuarina Rd to the North End Crosswalk are sealcoated.
  • Thanksgiving Holiday Schedule – No work will be scheduled over the Thanksgiving Holiday. Work will resume on Monday 12/2/19.

The schedule is weather dependent and is subject to change. Stay tuned for future schedule updates.