Project Update 10/29/19

  • Dune Fencing Installation – Crews continue installing the dune fencing posts along the east side of A1A along the back side of the sidewalk. Crews are working between Atlantic Ave. and the north end crosswalk.
  • Pedestrian Light Poles – Crews continue installing the new light poles along the sidewalk on the beach side of A1A. Crews are currently installing poles and moving south towards Casuarina Rd. Pedestrian traffic along the sidewalk may encounter brief sidewalk closures as the crew sets the new light poles into the ground. Parking spaces along A1A may at times be marked NO PARKING while crews install the new light poles. Once completed, those spaces will be reopened.
  • Roadway Improvements – The contractor is installing the electrical conduits which will power the new lighting along the sidewalks. The crew has started on the north end near Beach Drive and is moving south. This work takes place in the parkways and should have minimal impact to pedestrian traffic.
  • Tuesday, October 29: Atlantic Ave. & A1A Intersection – Crews are working in the southwest corner of the intersection placing the new truncated domes for the crosswalk. They are removing the existing pavers and installing the new white truncated dome pavers. This work is anticipated to be completed in one day.

SHARE