Project Update 9/9/2019

Construction Schedule: The Contractor’s work hours are 7:00 AM to 7:00 PM (Monday – Friday), weather pending. Detours may be put in place as needed, watch for signs.

Work Completed Last Week
Roadway Improvements:

  • Atlantic Avenue & Gleason Street Intersection: The Contractor milled the two middle lanes and paved the final layer of asphalt over the entire intersection.

Beach Improvements:

  • Dune delineation work including brush trimming near pathways and fence post installation is ongoing.
  • 35% of pathways complete.

Work Scheduled for this Week

Roadway Improvements:

  • Monday, 9/9/19 – Scheduled roadway work postponed until Tuesday, 9/10/19.
  • Tuesday, 9/10/19 – Atlantic Avenue & Venetian Drive Intersection: The Contractor will mill the edges of the intersection and pave the final layer of asphalt over the entire intersection.
  • Wednesday 9/11/19 thru Thursday 9/12/19 – A1A (Ocean Blvd.) and Casuarina Road: The Contractor will begin milling the pavement and replacing with new asphalt.
  • Friday, 9/13/19 – The Contractor will begin crosswalk improvements along A1A between Casuarina Rd. and Atlantic Ave. The Contractor will mill the pavement and replace with new asphalt. The work includes crosswalks near Anchor Park and Sandoway Center.

Beach Improvements:

  • Dune delineation work including brush trimming near pathways and fence post installation is ongoing.

SHARE