Project Update 9/30/19

Roadway Improvements

  • Thursday, 10/03/19 – A1A Crosswalks at Beach Dr. and the north end beach access: The Contractor will mill the northbound lanes along A1A at the crosswalks and pave with new asphalt. During the work traffic on A1A will be reduced to one lane of traffic thru the crosswalks with flaggers in place for alternating traffic thru the construction zone. Motorists can expect minor traffic delays. All lanes will be reopened at the end of each work day.
  • Work completed so far: Venetian Dr. and Gleason St. intersections on Atlantic Ave., Atlantic Ave. and Casuarina Rd. on A1A, and six crosswalks along A1A.
  • Upcoming work: The next stage of improvements will begin in mid to late October. This work will include stamping and painting the new asphalt and installing crosswalk pavement markings. Once scheduled, a timeline for those improvements will be posted.

Beach Improvements

  • The Contractor continues dune pathway fencing along A1A on the beach side. As of 09/30/19 approximately 50% of the Beach Improvements are completed. Crews are working on the south end of the project near Casuarina Rd.

SHARE