Construction Update 9/13/19

Roadway Improvements

  • Monday, 9/16/19 – A1A at Anchor Park and Sandoway Center: The Contractor will mill the northbound A1A lanes at the crosswalks to Anchor Park and Sandoway Center. Once the milling operation is complete, the Contractor will pave the final layer of asphalt. Traffic will be limited to one way traffic with flaggers. Motorists can expect minor delays going thru the construction zone. All lanes will be reopened by the end of work day.
  • Monday, 9/16/19 – Atlantic Ave. and Venetian Dr.: The Contractor will mill and pave the inside eastbound lane along Atlantic Ave. and Venetian Dr. During construction activity the two inside lanes along Atlantic at Venetian will be closed to traffic. The outside lanes will remain open.

Beach Improvements

  • Dune Fencing/Knee Wall: The Contractor continues to install the wooden posts for dune fencing. Crews are power washing and painting the knee wall along the double sidewalk area near Thomas Street.