Construction Update 9/12/19

Roadway Improvements

  • Friday, 09/13/19 – A1A & Casuarina Drive: The Contractor will pave the final layer of asphalt in the intersection. Traffic will be down to one way traffic on A1A as flaggers alternate between northbound and southbound traffic. Casuarina Dr. will be closed at A1A. Please follow detour signs along Gleason St. Motorists can expect minor delays going thru the construction zone. The intersection will be opened to traffic at the end of the work day.

  • Monday, 9/16/19 – A1A at Anchor Park – The Contractor will mill along A1A at the crosswalk to Anchor Park. Once the milling operation is complete, the Contractor will pave the final layer of asphalt. Traffic will be limited to one way traffic with flaggers alternating northbound and southbound traffic. Motorists can expect minor delays going thru the construction zone.