Construction Schedule: The Contractor’s work hours are 7:00 AM to 7:00 PM (Monday – Friday), weather pending.

Work Completed Last Week
Roadway Improvements:

  • Asphalt work has been completed for the Atlantic Avenue/Gleason Street intersection.
  • Asphalt work for the north and middle lanes has been completed for the Atlantic Avenue/Venetian Drive intersection improvements.

Beach Improvements:

  • Dune delineation work including brush trimming near pathways and fence post installation is ongoing.
  • 20% of pathways complete.

Work Scheduled for this Week
No work is scheduled for Friday, 8/30/19 or Monday, 9/2/19 in observance of Labor Day.
Roadway Improvements:

  • Asphalt work will continue for the Atlantic Avenue/Venetian Drive intersection improvements and is anticipated to be completed today, 8/26/19.
  • Tuesday, 8/27/19 – New curbs at the corners of Venetian and Atlantic Avenue will be installed. Expect periodic lane closure for the concrete pour. The intersection will remain open.
  • Tuesday 8/27/19 thru Thursday 8/29/19 – The Atlantic Avenue/A1A intersection work is scheduled to begin. This work consists of removing the existing brick pavers and installing new asphalt pavement. This work will be completed in phases, working in one lane at a time. Expect traffic delays during construction.
  • During the work hours of 7:00 AM to 7:00 PM detours may be used as needed for intersection work. Watch for signs!

Beach Improvements: