Project Updates

Project Substantially Completed!

16 Jan 2020

/

wpbeachmaster

The Beach Master Plan Phase 2 Improvements Project is now Substantially Complete. Any remaining work will be completed by the ...

0
0

Project Update 12/18/19

18 Dec 2019

/

wpbeachmaster

Dune Fencing Installation - Installation is 100% complete. Pedestrian Lighting - The new pedestrian lighting has been complet ...

0
0

Project Update 12/9/19

09 Dec 2019

/

wpbeachmaster

Dune Fencing Installation - Installation is near 95% complete. Crews are currently working near the North End Crosswalk insta ...

0
0